Project Budgetary Control validation error
Summary:
We have enabled the budgetary control at absolute level and budgets are created at task level and resource assigned for budgets are resource class ' Financial Resource' and budget is baselined as well.
While processing the payable invoice against project the validation is erroring due insufficient fund.
Does that mean we need add the expenditure type in budgets are resource if we have budgetary control enabled?