Past due Work orders in Production scheduling are not solved by the scheduler
Summary:
Hi Team,
We have couple of Work orders that are in unreleased status and their start date and end date is in past.
When we solve the production schedule, we can see past due work orders are appearing as firm even they are not firm in Oracle manufacturing and also system is not suggesting them to start on current date or in future.
ANy idea why Production scheduling is treating past due WOs as firm and how can we remove that.