Project Finish Dates are automatically updating when the project start date is updated.
Summary:
Project Finish Dates are automatically updating when I Update project start date in oracle fusion.
Content (please ensure you mask any confidential information):
Project start date was 1/1/25 and finish date was 3/31/26
When the start date was moved to 9/1/24, the finish date was automatically moved forward as well, which is not expected.
Version (include the version you are using, if applicable):
Oracle Fusion11.13.24.04.0 version
Code Snippet (add any code snippets that support your topic, if applicable):