You're almost there! Please answer a few more questions for access to the Applications content. Complete registration
Interested in joining? Complete your registration by providing Areas of Interest here. Register

Project Finish Dates are automatically updating when the project start date is updated.

edited Oct 17, 2024 4:47PM in Project Management 1 comment

Summary:

Project Finish Dates are automatically updating when I Update project start date in oracle fusion.

Content (please ensure you mask any confidential information):

Project start date was 1/1/25 and finish date was 3/31/26

When the start date was moved to 9/1/24, the finish date was automatically moved forward as well, which is not expected.

Version (include the version you are using, if applicable):

Oracle Fusion11.13.24.04.0 version



Code Snippet (add any code snippets that support your topic, if applicable):

Howdy, Stranger!

Log In

To view full details, sign in.

Register

Don't have an account? Click here to get started!