Production Scheduling not giving first preference to changeover duration
Summary:
Hi Team,
We are preparing for a demo on PS for a client. Based on our initial discussions, it seems they want to group all work orders by similar types of ice cream, and production scheduling should sequence the work orders based solely on changeover time, regardless of the need-by date.
I’ve completed the necessary setup, but I’m noticing that the system is still sequencing work orders based on the need-by date, despite the changeover duration I specified. Please let me know if I’m missing anything.
Content (please ensure you mask any confidential information):
Version (include the version you are using, if applicable):