WO are getting reschedule out
Summary:
Hello All,
The user released a Planned WO on 11 DEC, and the Planned Order Due date was 19 DEC. The Planning time fence is 5 days, so the Planning time fence date is 18 DEC. The Item has a Processing and post-processing lead time of 1 day.
Once the Planned Order was released the Start Date and Completion Date of the WO is 18 DEC. The WO is NOT FIRM . The Supply Plan ran on 12 DEC and now the system has asked to reschedule out the WO to 20 DEC. The Sales Order that is pegged to WO has a due date of 12 DEC, and all the materials are available to complete the WO.