Lead Times Used by Backlog Management
We are using Backlog Planning Rules of type "Supply chain availability search". We want to understand which lead times (Pre-Processing, Processing, Post-Processing, Fixed etc) are used by Backlog Management for each of the following order types:
(1) Make orders (we have components, BM need to make the FG using those components)
(2) Buy orders (BM needs to buy the component before making the FG)
(3) Transfer orders (BM need to transfer the FG from manufacturing location to DC in order to ship to customer from DC). Will it also consider Transit time for this?
We are seeing backlog management pulling in orders to dates by when we cannot have the material ready.