Not able to baseline Project Budget, the status changes back to Working-------------
Summary:
The Project budget is not able to submit. The Project budget goes back status as Working
Check the budget workflow and the condition is fulfilled
ProjectDff.budgetType		in		"New" , "Increase"
and
ApprovePlanVersionPayloadType.approvePlanPayload.businessUnit		is		"AUS"
and
Task.payload.planClassCode		is		"BUDGET"
and
ProjectBudget.totalRawCost.longValue()		between		"50,001" and "500,000"
and
ProjectClassification.projectClassCategory		is		"Preventive SIB"
and
ProjectTeamMember.teamMemberRoleName		is		"Asset Management Manager"
Content (please ensure you mask any confidential information):
Version (include the version you are using, if applicable):
Code Snippet (add any code snippets that support your topic, if applicable):
            Tagged:
            
        