Receipt accrual write off and project cost adjustment
Summary:
Receipt accrual write off and project cost adjustment
Content (please ensure you mask any confidential information):
PO with projects for $100 , Receipt $100 but AP Invoice matched to this project PO is $80.
Project Commitment and Actual Cost is $100.
Vendor not going to invoice for remaining $20 and business will create receipt accrual write-off.
Whether and how the accrual write-off will be adjusted in Project Costs.