Why Supply Plan does not plan items that have a Latest Acceptable Ship date?
Scenario:
- running constrained supply plan in Cloud Fusion
- Sales data comes through integration
- Testin the Original Promised Date to be sent into Latest Acceptable Date
- Running Constrained Supply Plan, no capacity constraint, enforce lead time = yes
- The Supply output shows the demand but no planned supply.
- The ending stock gets negative until the end of the planning horizon
- Backlog management doesn't provide a delivery date either
When I run supply plan without loading the Latest Acceptable Date, the plan suggests a supply but it is after the SO Original Promised Date.