Otbi report to compare budget revenue, baseline cost to project funded amount
I am triying to create a report to ocmpare project planned cost, budget revenue against the funded amount in contracts module by combining Project Finacial plan with Project Funding and dragging Contract Line and Task Number. However it does not work as below
Project parent/header tasks are assigned on the contracts module to each contracts line, while actuals and plan/budget gets recorded against the child task as below. When i bring 2 subject ares together and show contract line, i get disjointed/misleading view..
Please advice how to show PPM Financial plan actuals, baseline, PPM Budget budget revenue against funded amount from Contracts module with Contract line as column.