Calculation of Available Capacity in Process Manufacturing Constrained Planning
Summary:
How is available capacity calculated in Constrained Planning.
Suppose -
- We have a Process Manufacturing work definition with output batch Quantity 33333
- When we rollup the lead times Processing lead time comes to 1.47
- Since this is constrained planning, Only this processing lead time should matter (Variable, Fixed etc. should not matter)
- Now, If we have a demand for Qty 433333, then,
Total Demand Quantity = 433333
Batch Quantity = 33333
Number of Batches = 13.00012 (Total Quantity /Batch Quantity)
Time Taken For 1 Batch (Processing LT) = 1.47 Days
Therefore,
Total Production Time for All Batches (Total Quantity ) = 19.1101764 Working days (Time taken for one batch * Number of Batches)
Is the above calculation correct ?