Is there a case the WIP isssue transaction costed after completion trasaction?

in Costing 8 comments

Summary:

I just start supprting cost module for my customer now a days.

I encountered the work order which I can not understand how calculated and costed.

My quiestion is "Is there a case the WIP isssue transaction costed after completion trasaction?" as below content.

Content (please ensure you mask any confidential information):

When user operate below, is it possible to consider WIP issue cost after wip completion?

As a prerequisite the ess job "Create Cost Accounting Distributions" (Cut Off is May-31) was executed on 2025/05/21

I checked above work order in "Review Work Order Cost", both of input and output cost has incude "Material Issue" item cost.