Is there a case the WIP isssue transaction costed after completion trasaction?
Summary:
I just start supprting cost module for my customer now a days.
I encountered the work order which I can not understand how calculated and costed.
My quiestion is "Is there a case the WIP isssue transaction costed after completion trasaction?" as below content.
Content (please ensure you mask any confidential information):
When user operate below, is it possible to consider WIP issue cost after wip completion?
As a prerequisite the ess job "Create Cost Accounting Distributions" (Cut Off is May-31) was executed on 2025/05/21
I checked above work order in "Review Work Order Cost", both of input and output cost has incude "Material Issue" item cost.