Does Production Scheduling Honor Lead times ?
Summary:
I see that for an Item, The Supply Constrained Plan is honoring the long lead time of a component item and suggesting planned order for the finished item 6 months in the future (honoring 6 months lead time on the component item)
However, Production scheduling is taking the need by date on the planned order and scheduling immediately neglecting the lead time of raw material Item
Does production Scheduling have visibility to lead time and honor lead times? Is there any setup I'm missing which would ensure that the Supply Plan and Production Scheduling planned Orders are in sync?
Also, I'm not able to see any data in the on-Hand Inventory table.