Question on Resource Exceptions and Forecast Consumption in Constrained Supply Plan
Summary:
I’m running a constrained supply plan for a 4-month horizon in Oracle Fusion Supply Planning. I’ve come across a confusing behavior related to resource exceptions and forecast consumption.
Here’s the scenario:
- My forecast demand for the 2nd month is 1250 MT.
- My resource usage is 0.7 hours/MT.
- The actual sales orders for that month are:
- 400 MT on 11th
- 350 MT on 20th
- 500 MT on 25th
- So, total demand = 1250 MT.
There are 22 working days in the month, and the resource (a machine) has 24 hours/day available with a capacity of 1 (i.e., one machine). So:
- Available capacity = 22 × 24 = 528 hours
- Required hours
0