What is the best way to manage Facility Schedule Exceptions year over year?
Summary:
We are looking for the best way to Manage Facility Schedule Exceptions in Oracle Fusion. Our calendars are country specific and with different schedule exceptions entered for each calendar. However, Oracle does not allow same name for exceptions if we are trying to setup the same holiday for multiple years - For example -
Christmas - 12/25/25
Christmas - 12/25/26
It seems that we have to delete one exception before creating the same holiday for the next year.
We need to configure holidays for multiple years since the Planning system is using these dates to schedule the Planned orders only on working days. Can the experts here suggest the best way to handle this? This seems like a basic requirement for most customers.