Uninvoiced Receipt Accrual - Import to Project / PPM
Hi everyone,
My name is Donny, and I have a question on Uninvoiced Receipt Accrual, specifically with regards to importing the cost associated with it into Oracle Project.
Below are steps I followed to create the Uninvoiced Receipt Accrual:
1. Receive in procurement. Ensure the PO has a project ID associated with it
2. Transfer Transactions from Receiving to Costing
3. Transfer Costs to Cost Management
4. Create Uninvoiced Receipt Accruals
5. Uninvoiced Receipt Accrual Report
6. Create Accounting - draft then final - for Receipt Accounting
7. Import Costs in Project. Ran with Cost and Receipt definitions
After performing all steps, I still cannot see the cost imported into PPM.