Oracle Fusion Supply Plan Not Breaking Down Make Plan Demand on a Daily Basis (MPS/MRP Setup)
Hello Oracle Community,
We are currently facing an issue in our Oracle Fusion Supply Planning setup, and would appreciate your help.
Scenario Overview:
- We have 5 Assembly Items on an MPS/Make Plan
- Each is built from 5 Component Items (also on MPS/Make Plan)
- Each component is further built from 5 Subcomponent Items on an MRP/Buy Plan
- Demand for the Assembly Items is on 1st September
- Subcomponent lead times are correctly honored, and the system is pulling planned orders for these Buy items starting from 15th August as expected
The Issue:
While the system is honoring lead times for Buy Plan (MRP) items, it is not breaking down the Make Plan (MPS) demand on a day by day basis. It is generating a single large planned order for the entire quantity on the demand date (1st September), instead of spreading or phasing the planned orders according to capacity or lead time availability.
0