Oracle PPM - Not able to update Project Tasks DFF-Attribute with FBDI

Summary:

Hello Team,

We have created the Project template with Project Finish date is blank and all top tasks(without any child tasks) with Plan start date and Planned finish date defined.

When we are trying to update Project tasks DFF-attribute via FBDI keeping tasks planned date same, we are getting error# You can't have the planned dates for a task that are outside the planned start or finish dates of its summary task or the project.

However we can update the Tasks DFF-Attribute via application without any error.

Please suggest, if you face this issue and any workaround.

Thank You!