Processing lead time for Buy items not respected in plan
Summary:
Hey all,
i am running a constrained supply plan and i have given processing lead time for several different sub-component items(Buy items). After running the manufacturing plan, the output shows that system does not respect the lead time given.E.g; if lead time for sub component items end at 15th of month,i expect the production to start from that date.But the system says that plan start date is 1st of month and start the production from that date meaning sub-component items are available from that day.
Plan does give an exception for orders with insufficient lead time stating all the sub-component items and the compressed days and ratio.