Project Costing Based on Material Issuance (Consumption-Based Costing)
Hi All,
Greetings of the day…!
We have a business requirement related to Project Costing for a Construction-based business where materials like cement bags are procured and stored, and only the materials issued to the project are to be considered as project costs.
Actual process in Projects:
- A Project is created → PJC_1
- A Purchase Requisition (PR) is raised against the project → PRC_1 for $500✅ Cost reflected in Project as Purchase Requisition Committed Cost = $500
- A Purchase Order (PO) is created from the PR for $500✅ Cost moved to PO Committed Cost = $500❌ PR Committed Cost = $0
- Material is received against the PO for $500✅ Committed Costs cleared✅ Receipt & Cost Accounting processed✅ Cost imported to Project →