25C RSSP feature testing Use Lead Times to Determine Delivery Dates for Requisitions

edited Aug 14, 2025 5:45PM in Self Service Procurement 8 comments

Hi,

I have a question regarding the 25C feature - Use Lead Times to Determine Delivery Dates for Requisitions.
https://docs.oracle.com/en/cloud/saas/readiness/scm/25c/ssproc25c/25C-ssproc-wn-f35729.htm#Steps-to-Enable

The pre processing and post processing days are defined at the Item org level.

When we search and create a requisition through RSSP, the requested delivery date isn't looking at the processing days defined for that Inv org (ours is a 1:1 relationship between Inventory Org and REQ BU). Instead it is still looking at the value defined in the profile option - POR_REQUESTED_DATE_OFFSET