Allocation behavior when using "Allocation Amount Type"

Hello everyone! Hope you are doing great!

I have a question regarding "Allocation Amount Type" when setting up the allocation rules in EPCM. I have a situation:

  1. The Calculation Thread is set as 4.
  2. The source amount is 100. Need to split by 4% to Target A, 6% to Target B, 10% to Target C and 80% to Target D
  3. Set up four rules with the same source combination. In "Allocation Amount Type", I set rule A as Percentage with 4, rule B as Percentage with 6, rule C as Percentage with 10 and rule D as Percentage with 80.
  4. All rules are having the same sequence. They are in the same ruleset. The ruleset is set as "Parallel Calculation"