What all action planners can take to make sure a Sales Order can be expedited
Summary:
What all action planners can take to make sure a Sales Order can be expedited - SSD can be moved to earlier date (Yes or no) by checking the capacity and material availability in unconstraint Supply plan. ( both for MTO and non MTO Orders)
- Supply and Demand - ready to Build Percentage and quantity
- Build Plan - What items are shortage and which resource are overload
- MOPS - Manage Order Promising Demand - Check availability
- Demand at Risk fulfilment - checking all recommendation
- Production Scheduling - Minimize change over time by sequencing the work order
Does the planner have to look at all these places to get into a conclusion if a sales order can be expedited?