Handling Temporary Shutdown and Component Transfers Across Organizations
Summary:
Hello Community,
We are using Constrained Supply Planning in Oracle Fusion and have the following scenario:
We manufacture an assembly item in Organization 1. Due to a planned 10-day shutdown in Org 1 (e.g., for maintenance), we would like to temporarily transfer manufacturing of this assembly item to Organization 2 during that period.
Additionally, the assembly item uses component items that are manufactured in different organizations, not in the assembly orgs (Org 1 or Org 2). During the shutdown, we need the plan to also ensure that the components are transferred to Org 2 (the temporary manufacturing org) to support assembly there.
Could you please advise on: