RP-25C-RP Plan not honoring LT & Carrier Calendar, hence all the suggested dates are not as expected
RP Plan - BSM Replenishment Plan -1BL/BD
Item# - 417853
Buy from Supplier - Bosch Thermotechnology Ltd
Site- WORCEST
Pre and Post processing LT = 0
Processing LT = 5
No ASL LT.
Carrier Calendar = Wednesday Delivery
Sales Order 50 qty, GOP suggested SSD as 27/8 which is working as expected.
But when we ran the above RP plan, RP Plan suggesting Planned order of 29 qty with 2/9 as due date, which doesn't honor the LT and also it dint honor the Wednesday delivery carrier calendar.
I checked the same in SP Plan, SP Plan is behaving as expected