How to enable planning to pick a supplier for a buy item based on supplier lead time

We are trying to setup planning to suggest Suppliers based on the "Supplier Lead time" value in the item's ASL collected into Planning. We have done below setups for the same.


  1. Created two Global ASLs for the item with different suppliers in Procurement.
  2. Collected the ASLs to Planning. Collected ASLs are visible in the "Suppliers" table in Plan inputs.
  3. Performed FBDI Load using the "ScpApprovedSupplierListImportTemplate.xlsx" to load the Supplier Lead Time (Processing Lead time column in the FBDI file) for both the suppliers. The job Load data from Flat files job got completed successfully without errors.
  4. Created Sourcing rules for the item in Supply Plan with the below details.