Forecast ETC Revenue Calculation
Summary:
It appears to me ETC revenue in forecasts for future periods are calculated by spreading the amounts evenly based on contract line project funding amount.
Please confirm my understanding is correct?
How do I configure ETC revenue in forecasts by each periods are calculated based on contract line revenue plan method? We have a process revenue configurator logic and would like the application to derive the revenue amounts from revenue plan instead of spreading evenly. Is this possible at all?
Content (please ensure you mask any confidential information):
Version (include the version you are using, if applicable):
Code Snippet (add any code snippets that support your topic, if applicable):
Tagged:
0