Unable to use Person Legal Employer Name in Projects Miscellaneous Cost SLA
Summary:
We have a requirement to compare the provider and receiver LE in Miscellaneous cost SLA.
These are employee compensation cost imported into PPM as Miscellaneous cost through custom source.
Receiver LE - We have Project Legal Entity Name or Project Legal Entity ID as the source
Provider LE - We do not have Provider LE as source in Projects SLA.
Hence, we tried to use Person Legal Employer Name but the condition is not working.
"Person Legal Employer Name" != "Project Legal Entity Name"
Content (please ensure you mask any confidential information):
Version (include the version you are using, if applicable):
Tagged:
0