Which Processing Lead Time BUY Planned Order Takes ? How it takes Purchase LT at Item level.
Summary:
We Have the BUY Type Item- EYB016
At Item Level - Process Lead Time = 25 Days
At ASL Level- Process Lead Time = 20 Days
Result-
Planned Order is always taking the Lead Time at ASL level i.e 20 Days.
Scenario Tested
1) At Item Level / PDH-
Enforce Purchasing LT= NO
Planned Order is taking the Lead Time at ASL level i.e 20 Days.
2) At Item Level / PDH-
Enforce Purchasing LT= YES
Planned Order is taking the Lead Time at ASL level i.e 20 Days.
Please Advise-
What can be done so that Planned Order Takes the Processing Lead time at Item level i.e 25 Days ? ?