Cycle Count Location Logic

Summary:

Let’s assume we have 15,000 locations in total.

As per the current setup, the condition runs for less than 30 days (Location-Last count time d<30) , and the maximum task limit is set to 70 in the task template.


This means 70 locations are cycle-counted per day, resulting in 2,100 locations per month (70 × 30).

My question is: What happens to the remaining 12,900 locations?
After the 30-day period, when the condition runs again, will it:

  • Only process the same 2,100 locations again, or
  • Include the remaining 12,900 locations that were not previously counted, along with the new cycle?