Budget showing incorrect consumption amounts

Summary:

Project# xyz has a Total Budget of 81,417 $

Total Cost is 81,100.8 $
There is not Commitment cost active.

However, when we tried to enter the cost for remaining amount of 316.2 $ system is giving fuds error.

After thorough investigation, it is noted that 187.33 $ is stuck as obligation and nowhere in PO/PR/INV that can be see and this obligation is not getting released even after the UPPD run in Delete and Summarize method.

Content (please ensure you mask any confidential information):


Version (include the version you are using, if applicable):

26A (11.13.26.01.0)

Code Snippet (add any code snippets that support your topic, if applicable):