PPM Commitment Getting Created Before PR/PO Approval – Need Help with Budgetary Control Behavior
Summary:
When creating a Purchase Requisition (PR) or Purchase Order (PO), the system is creating a commitment in Projects even when the PR/PO is still pending approval.
Our expected behavior is that commitment should only be created after the PR/PO is approved, since our budgetary control setup allows consumption only after approval.
Current Setup
Based on our configuration:
- Budgetary Control is enabled
- Reservation Point is set to “Approval” for both Requisitioning and Procurement
(screenshot attached) - Encumbrance accounting is enabled