Recurring Schedule Exceptions Across Multiple Years
Summary:
Recurring Schedule Exceptions Across Multiple Years
Content (please ensure you mask any confidential information):
Hi,
My objective is to define a new schedule in "Manage Project Schedule" and associate a schedule exceptions with it.I want to create a single schedule covering multiple years (for example, from 01/01/2026 to 31/12/2030). Within this schedule, I would like to define public holidays that recur every year (2026, 2027, 2028, and so on) as schedule exceptions.However, when I try to create an exception in "Manage Schedule Exceptions", I can only enter a single date for one specific year (for example 25 December for 2026), with no option to make it recurring for subsequent years, unless I manually duplicate it.Is