Lead Time Offset in BOR is considering the lead time of Phantom Item
Summary:
BOR`s Lead Time Offset and the GOP Lead Time are taking into account the Lead Time of Phantom Item, while Work Order and MRP are skipping it.
Content (please ensure you mask any confidential information):
We have the following setup:
Assembly Item 20192047
Processing Lead Time: 10
Pre: 3
Post: 1
Intermediary Phantom Item 10300662
Processing Lead Time: 11
Pre: 5
Post: 4
Component Item A75080738
Processing Lead Time: 7
Pre: 2
Post: 2
The BOR Lead Time Offset In Days for Assembly Item 20192047 is 26 Days (the sum of Lead times in bold). It is taking into account the Lead Time of Phantom Item 10300662. GOP simulation is also taking into account the Lead Time of Phantom Item (total of 37 days).