FCCS Additional Cube Enablement – Recommended Approach for Bulk Entity Enablement
Hi Experts,
We recently enabled an additional cube (Console2) in FCCS and are enabling existing Entity members for the new cube using the Dimension Editor UI.
We are observing that enabling a single Entity member takes approximately 3 minutes. Since we have a large number of entities, this process is very time-consuming.
Is there a recommended bulk method to enable/import existing Entity master data for a newly enabled cube?
Note - We also tried using the Import option for the Entity dimension, but the import has been running for over 4 hours without completing.
Thanks in advance for your guidance.
Regards,
Tagged: