demand plan run process ends with warningSummary: during the demand plan run process. The process ends with the following warning: "The plan data definition is incomplete. You must run this plan with the Refres…Youssef_Abdellatif 37 views 6 comments 0 points Most recent by Caroline Durairajan Supply Chain Planning and Collaboration
-
Production Scheduling - SolveI need help for understanding solve by a Order. I have WO539 with need by date 05/08/2025 when I run solve the system schedule my order by 17/09/2025 but all her pegging…Maria Rosa Gonzalez 5 views 1 comment 0 points Most recent by M. Bolsinger-Oracle Supply Chain Planning and Collaboration
-
work definition not getting collected in supply planningSummary: work definition got collected into plan inputs but not in supply plan. work method is discrete, type is standard. only one resource is attached to work definiti…SARTHAK GOSWAMI 20 views 4 comments 0 points Most recent by Yann Consolin-Oracle Supply Chain Planning and Collaboration
-
Routing & Resource Showing in Plan Inputs but not showing in Supply planSummary: We are facing a issue where we are able to collect and see Routing & Resource in Plan Inputs but when we ran the supply plan we are not able to see the routing …Akshaykumar Trivedi 23 views 5 comments 0 points Most recent by Yann Consolin-Oracle Supply Chain Planning and Collaboration
-
Production Scheduling is not taking in account changeover rulesSummary: We are trying to set up PS using work definition operrations DFFs, the value set is set as independent. The changeover rules have been configured and all the sc…F_Suarez 59 views 6 comments 0 points Most recent by M. Bolsinger-Oracle Supply Chain Planning and Collaboration
-
Can we include a custom DFF at Work Order level in Production Scheduling?Summary: Hello, We would like to create a custom DFF in the work execution on the Work Order screen. Is there a way to pull this DFF into Production Scheduling as well? …Thushara Unnikrishnan 24 views 5 comments 0 points Most recent by M. Bolsinger-Oracle Supply Chain Planning and Collaboration
-
Work order operation DFF in production Scheduling not showing change overSummary: Used Work order operation DFF attribute for change over and created work orders for that item , but in production scheduling it is not showing the change over. …Saroj Maharana 5 views 1 comment 0 points Most recent by M. Bolsinger-Oracle Supply Chain Planning and Collaboration
-
Gantt Chart question in Production SchedulingSummary: Gantt Chart question in Production Scheduling Content (required): Team, could you please help me with this question? When a resource has more than 1 unit assign…Basab Roy-Oracle 89 views 15 comments 0 points Most recent by M. Bolsinger-Oracle Supply Chain Planning and Collaboration
-
How is Average Daily Demand calculated in Replenishment Planning versus Supply Planning?In Oracle Fusion Cloud, is there a difference in how the Average Daily Demand measure is calculated between the Replenishment Planning and Supply Planning modules? Speci…RajeshKenchi 8 views 0 comments 0 points Started by RajeshKenchi Supply Chain Planning and Collaboration
-
Unconstrained Supply plan fails with ABP Netting RuleSummary: We defined Planning attributes an ABP netting rule setup and collected and run SP with Neteting rule attached. However, plan is failing with below error: Conten…
-
Supplier Shipping CalanderHello Experts, I’m encountering an issue with the FBDI template 'ScpCalendarAssignmentsImportTemplate'. I’ve filled in all the required fields and successfully imported …Sam Bandara 49 views 11 comments 0 points Most recent by Sam Bandara Supply Chain Planning and Collaboration
-
Is it possible to load supplier bank details directly under the supplier profile using FBDI?Summary: The usual process is: after creating the supplier profile, address, site, and site assignment, we load the supplier bank details, which are then available at th…
-
How to set up a calendar for the Fixed Order Cycle policy?Summary: The supplier only takes order on a specific day. Goal is to create a calendar that only looks at one day a week and attach this to the Fixed Order Cycle Policy.…Michael Parduhn 39 views 12 comments 0 points Most recent by Thierry Lamote Supply Chain Planning and Collaboration
-
DM ORA20003 aquiring lock for shared data table.retry limit exceeded for table MSC_AGGR_MEASURE_DATASummary: AggregatePlanningCollected Data job Errors ORA20003 aquiring lock for shared data table..retry limit exceeded for table MSC_AGGR_MEASURE_DATA Content (please en…Catherine Alequin 15 views 2 comments 0 points Most recent by Scott Malcolm-Oracle Supply Chain Planning and Collaboration
-
Purchase Orders which are not firm are getting rescheduled in within the Items lead time.Summary: We are observing one different bheviour of Constrained Planning in which we observed that the Purchase Orders which are not firm are getting rescheduled in with…Neeraj Thool 40 views 5 comments 0 points Most recent by Neeraj Thool Supply Chain Planning and Collaboration
-
Hyperparametertuning - Last attempt at Tuning questionSummary: After we run the Demand Plan with Sample Size = 100, we realized that ~ 2,000 out of ~16,000 combinations have 01-01-2000 as the Last Attempt at Tuning These co…
-
How to switch the production to an alternate organization?Summary: My scenario is that an item 1 demand is in ORGANIZATION SR1.It is made in this org Using a resource A.I made the resource unavailable for 10 days. Now, i want t…Zeshan12 20 views 6 comments 0 points Most recent by Yann Consolin-Oracle Supply Chain Planning and Collaboration
-
Error on table MSC_ST_MEASURE_DATA, column TIM_LVL_MEMBER_VALUE. ORA-01841:(full) year must not be 0Summary: We wanted to load the item shipment history to a new custom measure. So, we have created a new measure by dupliating the Shipments History: Shipped Item by Requ…Sangeetha P 5 views 0 comments 0 points Started by Sangeetha P Supply Chain Planning and Collaboration
-
RELEASE Planned Orders (buy items) with Implement Firm as YES, but PO created in EBS are not firmSummary: when Buy item Planned order is released from Supply planning cloud with "Implement Firm" as yes, still Requisition/PO created in Oracle EBS R12.2.10 is not firm…MD MERAJUDDIN 27 views 5 comments 0 points Most recent by Thierry Lamote Supply Chain Planning and Collaboration
-
How to stop cursor automatically moving to editable field on selected line in "Supplies and Demands"Summary: Automatic cursor moves to 1st editable field on selected line in "Supplies and Demands" table. Business users are NOT liking this and wants to stop this automat…MD MERAJUDDIN 11 views 0 comments 0 points Started by MD MERAJUDDIN Supply Chain Planning and Collaboration
-
How to Plan Supplies for ETO Item?Summary: We would like to understand how Supply planning plans supplies for ETO assembly item on a SO as ETO item will not have an Item structure WD initially. Any docum…
-
where to see the subinventory stock after constrained supply plan run?Summary: After assigning subinventory to an organization and to respective forecast.The subinventory netting is also enabled in plan options. Where we can see the manufa…Zeshan12 32 views 7 comments 0 points Most recent by Gururaman Subramanian-Oracle Supply Chain Planning and Collaboration
-
Load planning data result in Warning (import planning catalog)Hi experts, I am trying to load the custom catalog ScpCatalogImportTemplate.xlsm using FBDI. the FBDI has 3 tabs, I use 3 of them to import the catalog and item-categori…lala009 21 views 4 comments 0 points Most recent by Gururaman Subramanian-Oracle Supply Chain Planning and Collaboration
-
The FG planned orders not creating dependent Demand for componentsSummary: We have planned orders for an FG item but this quantity is not generating dependent demand for its components. We have this error in the plan messages. For item…Sangeetha P 38 views 14 comments 0 points Most recent by Yann Consolin-Oracle Supply Chain Planning and Collaboration
-
Supply Chain Planning FBDI Templates MacSummary: Currently SCP (Supply Chain Planning) FBDI Templates are working only on Windows Version of Excel. Customers and SI are asking if a version compatible with Offi…Paolo Prandini-Oracle 9 views 0 comments 1 point Started by Paolo Prandini-Oracle Supply Chain Planning and Collaboration
-
Periodic automatic replenishment policy calculations in Replenishment PlanSummary: Hello all, We are currently in 24D and looking to implement “Periodic automatic replenishment (PAR)” policy type in our Replenishment plan - to get the suggeste…Sathish Sami 93 views 8 comments 0 points Most recent by Jayesh Agrawal-Oracle Supply Chain Planning and Collaboration
-
Shipment Forecast is not generated in by the system in demand planning for all the itemsSummary: From yesterday, demand planning system is not generating shipments forecast for all the items even though previous six months shipments history is available for…Sangeetha P 20 views 3 comments 0 points Most recent by Sangeetha P Supply Chain Planning and Collaboration
-
How does changeover rule work for item EFFSummary: Hello, We have an item EFF called thickness, which corresponds to the thickness of the item and for items of different thicknesses, different resources are used…Thushara Unnikrishnan 50 views 9 comments 0 points Most recent by M. Bolsinger-Oracle Supply Chain Planning and Collaboration
-
Purchase Requisitions are not getting created after releasing the planned ordersSummary: Hi All, We are trying to release the planned orders from the replenishment planning and even we can see its transactions are getting created in SCO with out any…SwapnnilPande 96 views 5 comments 0 points Most recent by Manoj kallapu Supply Chain Planning and Collaboration
-
Can we make resource unavailable in an inventory organisation ?Summary: Can we make resource availability in system unavailable in an inventory organisation and make item using resource in 2nd rank inventory organisation? Scenario: …Zeshan12 29 views 7 comments 0 points Most recent by Santosh V-Oracle Supply Chain Planning and Collaboration