This post answers all audience questions during the Cost Planning Customer Connect session on 10/18/2018.Content
This post addresses all the questions asked during the Customer Connect session – “Deep Dive into Cost Planning” scheduled on 10/18/2018.
Q: Is it possible rollback the rollup if it is inaccurate? If not, is it possible to add this in product raod map?
A: You have the option to delete a cost scenario that has rolled-up costs. A cost scenario can be deleted as long as it is not published.
Q: Can we define overhead at resource level ?
A: Yes, while entering resource rates, you can define overhead by selecting the cost element of type “Overhead”.