Creating Task/Subtask for Project which already have task created

Accepted answer
36
Views
2
Comments
edited Jun 2, 2019 3:12PM in Project Management 2 comments

Summary

Creating Task/Subtask for Project which already have task created

Content

Hi Team,

I need to create task/subtask for a project which already task/subtask created.

What I observed is, createTask operation of ProjectTaskServiceV2 is creating task for a project which don't have any task created.

If I need to create task/subtask using updateTask method, how to create it?

Also how to create subtask for a task?

We are creating task using createTask method as-

   <typ:tasks>
            <main:ProjectId>300000011505788</main:ProjectId>
            <main:TaskName>2</main:TaskName>
            <main:TaskNumber>2</main:TaskNumber>
            <main:PmTaskSourceReference>2.1</main:PmTaskSourceReference>
            <main:PlanningEndDate>2019-05-31</main:PlanningEndDate>