You're almost there! Please answer a few more questions for access to the Applications content. Complete registration
Interested in joining? Complete your registration by providing Areas of Interest here. Register

Funds Check fail on a requisition

edited Jul 5, 2019 3:48PM in Project Management 1 comment

Content

We have a project that expired 12/31/19 and the end-user is trying to use it on a requisition. The check funds is failing saying the budget date of 7/5/19 is not between the project dates of 8/1/16 and 6/30/19...why is it showing a June 19 end-date when the project page is 12/19?

XCC-675370

Version

R13-19B