Summary

Have an adjusted version to copy

Content

Hi,

We have a bottoms up budget that we made top level adjustments to.  I thought we could accomplish this by having 2 child versions added together with a parent.  The totals work when retrieving in Smartview, but I'm unable to copy the parent version to a snapshot version.  The rule says it's completed, but there's no data in the target version.  I'm thinking it may be due to the Type or Data Storage used.  Has anyone done something like this in the past or have an idea what was set up incorrectly?