Hi Folks,
20A FBDI used to import Standard PO, few PO are completed with Open Status but many of the PO's are completed with "Incomplete" Status. No Budget Controlled or Encumbrace used by client.
FBDI Template: Approval Action set as BYPASS
PO Interface, APPROVAL_ACTION is updated as 'BYPASS'
Any helps is appreciated. Thanks.