Scenario:
Create a PR with 3 lines:
Line 1: Item A : Total Line Amount = 100 USD
Line 2: Item B : Total Line Amount = 100 USD
Line 3: Item C : Total Line Amount = 100 USD
PR is Approved.
Now in Process Requisition, Buyer will only select Line 1 & Line 2 and create a PO
Once PO is created, buyer would now add another new line as Line 3 which has no reference of PR and the PO line 3 amount is 200. Also the buyer would change the Line 1 total amount to 50 USD which is less than the amount compared to PR line amount.