To create dependencies on Summary tasks

edited Jun 24, 2020 11:01AM in Project Management 3 comments

Summary

20A

Content

Hi All,

 

Could you please let me know if you we can create a dependencies on Summary tasks. 

 

When i try to create the dependencies of the main task i get the error as "You can't create dependencies on summary tasks." 

Scenario:

Task Number Task Name Start Finish Dependency
1 (Main Task)    Pre-Implementation Work 18-02-2020 24-06-2020  
1.1 (Sub Task)       PO Release 18-02-2020 18-02-2020  
1.2(Sub Task)       Project Initiation (Kick-Off) 19-02-2020 25-02-2020  
2(Main Task)       PO Release to OEMs 02-03-2020 25-05-2020  
2.1(Sub Task) PO release to vendor 02-03-2020 06-03-2020 1
2.2(Sub Task) PO release to OEM