To create dependencies on Summary tasks
Summary
20AContent
Hi All,
Could you please let me know if you we can create a dependencies on Summary tasks.
When i try to create the dependencies of the main task i get the error as "You can't create dependencies on summary tasks."
Scenario:
Task Number | Task Name | Start | Finish | Dependency |
1 (Main Task) | Pre-Implementation Work | 18-02-2020 | 24-06-2020 | |
1.1 (Sub Task) | PO Release | 18-02-2020 | 18-02-2020 | |
1.2(Sub Task) | Project Initiation (Kick-Off) | 19-02-2020 | 25-02-2020 | |
2(Main Task) | PO Release to OEMs | 02-03-2020 | 25-05-2020 | |
2.1(Sub Task) | PO release to vendor | 02-03-2020 | 06-03-2020 | 1 |
2.2(Sub Task) | PO release to OEM |
Tagged:
0