Cancelled PO Schedule not available again to reprocess into a new Purchase Order
Summary
Cancelled PO Schedule not available again to reprocess into a new Purchase OrderContent
Hi All,
we are testing currently the functionality of "cancel unfulfilled demand". At the requisition BU level, we have enabled the setting:- Cancel unfulfilled demand set to "Optionally". Reason is we wanted to give buyers the option to cancel unfulfilled demand at the PO level.
Now we create a requisition, generate it into PO, have the PO line split into multiple schedules. for this lets assume the PO has one line of 1000 qty, schedule split into 600 qty and 400 qty. Now we do a change order, cancel the schedule of 400 qty. During the cancel schedule, we get an option to have the demand cancelled (Yes/No). We set it to no. The change order is submitted for approval. Once the approval is complete, the change order is not getting approved. It is stuck at pending approval Whereas when the cancel unfulfilled demand is