How to see / calculate PO Commitment against a Project
Content
Hi,
Fusion Version: 20B (11.13.20.04.0)
I've been asked to investigate why a Dashboard report "Project Budget vs Actual" includes a Commitment value against a PO which has been cancelled and whose receipt has been corrected back to zero.
I realise the report logic might not be correct.
In the "old" world of R12 I could have gone to Project Status Inquiry to validate if the commitment was visible via the front-end, which would help rule out any issues with the report.
- Is there any way via the front-end to see the commitment value against either a Project, or the Contract the Project is associated with?
0