Using fixed order quantity results in planning creating pegged work orders with the quantity in frac

edited Dec 7, 2020 9:28PM in Supply Chain Planning and Collaboration 1 comment

Summary

Want to ensure pegged quantity is an integer when using fixed order quantity

Content

We are using constrained supply plan without projects.  Client wants to release WO tied only to a specific SO and doesn’t want 1 WO pegged to 2 different SO. So we used fixed order quantity of 1 but plan recommends 2 WO with pegged quantity in fractions. Is there a way to ensure pegged quantity is integer since items aren’t divisible?