Requested delivery date not calculating as per BPA setup lead time days

Received Response
18
Views
1
Comments
edited Dec 29, 2020 9:43AM in Purchasing 1 comment

Summary

Requested delivery date not calculating as per BPA setup lead time days

Content

Hi All,

We have a BPA created for a couple of items for which there is lead time days setup in the agreement. But when the PO is created from requisition, the requested delivery date calculation remains unchanged and is taken from requisition and not calculated. The offering "Automatically Determine Requested Delivery Date Using Agreed Lead Time" is set to Yes and the feature is turned on.

Is there anything else I am missing or it will calculate only on standalone purchase orders.

Version

20D
Tagged: