Thank you for supporting the Cloud Customer Connect Community in 2024. It's a gift to work with you!

Look back
You're almost there! Please answer a few more questions for access to the Applications content. Complete registration
Interested in joining? Complete your registration by providing Areas of Interest here. Register
Get Started with Redwood for Oracle Cloud HCM   Begin Now
To ensure that questions get required attention from community members and are NOT left unanswered, it’s important for the author to indicate (by selecting “Yes” or “No” when prompted) whether the question was answered. (newly added) Please note that it is also important to respond to EACH comment your question receives. Your Yes or No response ensures an accurate status for your question.

For more information, please refer to this announcement explaining best practices for getting answers to questions.

Conversion formula limit time

edited Jan 26, 2021 9:00PM in Workforce Management 1 comment

Content

Hello experts.

I need a Conversion Formula (Global absence type duration) that actually limits the duration.
The schedule is default for the whole company from 6 to  22 hours. 
When user launches his day and doesn't look carefully it gives us 16 hours instead of 9 or 7 he actually worked based on his assignemnt working hours time.

Could anyone help wich paaremters may I use that might solve this issue? or if there is any other way to do it besides fast formula

Thanks


 