How to reconcile the OTL to Payroll to Project accounting
Summary
How to reconcile the OTL to Payroll to Project accountingContent
Hi,
We have a requirement to enter time sheet in HCM, that is giving feed to Payroll as well as Projects
E.g: Employee enters time sheet for 40Hours with $1,500 (as actual Payroll Cost)
Assumption we are using the same rate in Projects as well
So in Payroll the 1st accounting is
Payroll Exp -- 1500 (DR) --> Cash --1500 (CR)
When the OTL time sheet imports into PPM, and performing the accounting it is like
Direct Labor Exp --1500 (DR) --> Labor Clearing -- 1500 (CR)
at the time of reconcile, how we will move the clearing amount to which account?? what is the best practices here.