Q: How to change a Maintenance Org's Work Week from 5-Day to 7-Day?
Summary
How does one change a Maintenance Org's Work Week from 5-Day to 7-DayContent
Hello,
To quickly summarize the problem: I can change the maintenance org to a 7-day work week, but it does not seem affect maintenance forecasting, hence my problem. Is there some process I need to run to make that 7-day work week effective so it is used in maintenance forecasting?
Here's my story:
In our initial configuration of the maintenance organizations (we have four) we configured each to have a 5-day work week. That worked fine until we started forecasting work orders on assets that used a day-meter. The Daily Utilization Rate for each asset is '1' (obviously) and, for the Work Requirement, the Base Interval for the day-meter was 90 days. What we expected was that maintenance forecasting would schedule work orders 90 days apart.